Armenian NPP maintenance completed ahead of schedule

Armenian NPP maintenance completed ahead of schedule

ArmInfo. The scheduled  preventive maintenance at the Armenian Nuclear Power Plant has been  completed ahead of schedule. This was reported in a statement by the  ANPP press service.

As the source notes, the 2024 PPR was initially planned to be  completed on August 18, but thanks to the team's clear work, it was  possible to implement the program about a week ahead of schedule.

The station emphasized that after the repairs, the 4th and 3rd  generators of the second power unit of the Armenian NPP were  connected to the country's power grid on August 11 at 12:17. At the  moment, the station is operating in normal mode, observing safety and  reliability standards.

As part of the 2024 PPR, measures were taken to improve the  operational safety of the plant, in particular, a major overhaul of  the reactor unit, a major overhaul of the 3rd turbine and the 3rd  turbogenerator, routine repairs of the 4th turbine and the 4th  turbogenerator, a major overhaul of the reactor vessel, repair and  inspection of the metal of the reactor vessel and in-vessel devices,  replacement and inspection of the bearings of the drives of the  emergency control, compensating cassettes (ACC), a major overhaul and  inspection of the main shut-off valve. In addition to the employees  of the main NPP shops, experienced specialists from the companies  "Armatom", "Energoremgarant", "Volt Ampere", "IS ENERGY", "PROTERM",  "PROMMONTAZH", as well as specialists from Russia, Croatia, the Czech  Republic and Ukraine are also participating in the current work. We  will add that the current work was carried out as part of a project  to extend the unit's service life by 10 years - until 2036. The work  is being carried out by the company "Rusatom Service", which is part  of the Rosatom State Corporation.